SUBJECT: Major Project Update
This memo is the most recent update of major projects around our system that are either recently completed or to be done in the next 60-90 days. Not all major cities will be shown since some projects’ completion dates occur beyond the next 90 days.
All Cities: Bag tag issuance at kiosks is now operational in the cities where we had already installed them in the ticket counter. The next phase is to move gate-area kiosks to the ticket counters at additional cities with a goal of having 20 cities done by year-end and all cities done by 2nd quarter 2005. A shortage of IBM units has somewhat delayed the installation schedule.
BNA: The project to expand our ticket counter, ATO, and bag make-up facility by swapping space with AA continues. The new ticket counter and make-up carrousel will be in by September 15th, AA will move to their new space in October, and all work will be done by November 1st.
ISP: The four new gate construction is complete and opened August 4th.
LAS: The C/D checkpoint has been expanded to 18 lanes (an increase from 9 lanes).
OAK: Work continues on the new Provo facility with completion expected by September 21.
ONT: Construction started August 4th to expand and renovate our BSO, including conversion of a storage area into the lobby. Expected completion is September 8th.
PHL: Work continues on our permanent Provisioning facility with move-in expected in October. (No change).
SAN: Provo will be relocated from under the concourse to a separate facility nearby giving us more space at a lower cost. Work has slowed somewhat due to some required building code work and we now expect to complete it in October. The new facility can be converted into a full-service Provo operation as flight activity warrants.
SEA: As part of the terminal expansion project we will move from gate B-4 to B-14 in early November. This will improve storage for ground handling equipment on the ramp and put more of our gates together.
Other Major Projects: Work continues on major projects in BWI, MCI, PHX and TPA with new gates at each of those cities opening starting in late 2004. More detail will be provided as we get closer to completion.
This memo is the most recent update of major projects around our system that are either recently completed or to be done in the next 60-90 days. Not all major cities will be shown since some projects’ completion dates occur beyond the next 90 days.
All Cities: Bag tag issuance at kiosks is now operational in the cities where we had already installed them in the ticket counter. The next phase is to move gate-area kiosks to the ticket counters at additional cities with a goal of having 20 cities done by year-end and all cities done by 2nd quarter 2005. A shortage of IBM units has somewhat delayed the installation schedule.
BNA: The project to expand our ticket counter, ATO, and bag make-up facility by swapping space with AA continues. The new ticket counter and make-up carrousel will be in by September 15th, AA will move to their new space in October, and all work will be done by November 1st.
ISP: The four new gate construction is complete and opened August 4th.
LAS: The C/D checkpoint has been expanded to 18 lanes (an increase from 9 lanes).
OAK: Work continues on the new Provo facility with completion expected by September 21.
ONT: Construction started August 4th to expand and renovate our BSO, including conversion of a storage area into the lobby. Expected completion is September 8th.
PHL: Work continues on our permanent Provisioning facility with move-in expected in October. (No change).
SAN: Provo will be relocated from under the concourse to a separate facility nearby giving us more space at a lower cost. Work has slowed somewhat due to some required building code work and we now expect to complete it in October. The new facility can be converted into a full-service Provo operation as flight activity warrants.
SEA: As part of the terminal expansion project we will move from gate B-4 to B-14 in early November. This will improve storage for ground handling equipment on the ramp and put more of our gates together.
Other Major Projects: Work continues on major projects in BWI, MCI, PHX and TPA with new gates at each of those cities opening starting in late 2004. More detail will be provided as we get closer to completion.